The first construction project from the Far East Freeway Study (PID# 76997) Phase 1 includes partially reconfiguring the system-to-system interchange of I-70 and I-270, and the system-to-service interchange of IR-70 and Brice Road by removing major weaving movements. The reconfiguration will separate the through and local traffic from I-270 and I-70 headed eastbound and to Brice Road. This project includes all the associated drainage, lighting, traffic control, utility relocation, and noise abatement to reconfigure the interchanges. CCI performed roadway design for a frontage road and utility design for approximately 2400 feet of water main relocation, which included trenchless crossing design under I-70. In addition, a sanitary sewer crossing of I-70 was also designed using trenchless methods. CCI also served as the Project Utility Coordinator.