Portsmouth Bypass (SR 823), Portsmouth Joint Venture Group. The project is a four-lane, divided, limited-access highway bypassing the City of Portsmouth in Scioto County, Ohio. This project is comprised of 16 miles of a new highway. CCI performed Storm Water Pollution Prevention Plans (SWPPP)...

PROJECTS_CCI_DIVERGING_DIAMOND

Challenge: While Diverging Diamond Interchanges (DDI) reduce congestion and improve safety, their innovative design can be confusing when first encountered by the public. ODOT wished to develop tools to inform the public on the benefits of the new design and how to properly navigate...

HRBT-Expansion-Project-Corridor-Concept.

Challenge: Provide a tool to effectively communicate the upcoming changes to the I-64 corridor as VDOT launches its $3.8B plan to increase capacity of one of the most congested traffic corridors in the U.S. Solution: CCI developed a 3D model from the design plans and created...

CCi projects civil Engineering 1055 oak street

These projects consisted of multiple utility designs to serve new commercial properties in downtown Columbus. Complete Water Service Plans were developed for each project. In addition, relevant design phase aspects of this project include open-cut construction, new service connections for multiple utilities including City...

The first construction project from the Far East Freeway Study (PID# 76997) Phase 1 includes partially reconfiguring the system-to-system interchange of I-70 and I-270, and the system-to-service interchange of IR-70 and Brice Road by removing major weaving movements.  The reconfiguration will separate the through and...

cleveland-ODOR-opportunity

The project is a Design-Build contract to construct a four-lane, divided, boulevard highway passing through the City of Cleveland in Cuyahoga County, Ohio. CCI performed utility design for approximately 9000 feet of water main, which included distribution mains and a bridge-mounted 30” transmission main.  Work...

Performed field investigation, hydrologic and hydraulic analysis and design and construction plans development for Household Sewage Treatment Systems (HSTS) elimination project in the Brooklyn/Cleveland Avenues project area which is comprosed of 22 residential homes along Brooklyn Avenue and seven business along Cleveland Avenue. The design includes...

city overpass at dusk

CCI worked with the City of Canal Fulton, Ohio to develop plans for the improvement of the Cherry Street (SR 93) and Locust Street (CR 228) intersection. Following the ODOT PDP, CCI developed, analyzed, and made a recommendation for a Preferred Alternative. In addition to...

CCI created an assessment and strategic plan for the migration of the CTSS to a new, open architecture infrastructure to implement future projects within the Transportation Division. The goal was to maintain system connectivity and interoperability, which included design of a new fiber optic network.  GIS...

A new Pump Station was designed and implemented to drain a series of large diameter storage tunnels under the near western suburbs of Cleveland to eliminate combined sewer overflow in wet weather events.  Our technicians and engineers used AutoCAD and Revit for 2D drawings and...